Link


Social

Embed


Download

Download
Download Transcript


[00:00:06]

GOOD MORNING.

TODAY IS THE 16TH OF JANUARY, 2026.

THIS IS THE ANTENNA REVIEW BOARD IN THE TOWN OF GREENBURG.

I'D LIKE TO TAKE ATTENDANCE FIRST.

CAPTAIN LETTER OF SKE.

THAT'S ME.

I'M HERE.

DIANE TORRA HERE.

DONNA SHAMAN IS NOT WITH US HERE TODAY.

UM, AND WE HAVE A QUORUM PRESENT IN THE TOWN OF GREENBERG IN A PUBLIC FACILITY ACCESSIBLE TO ALL.

UM, FRANCIS SHEEN.

OUR TOWN LIAISON IS WITH US.

AND STEVE, TIM MATEO IS HERE IN PERSON FROM AEROSMITH DEVELOPMENT.

AND ON ZOOM WE HAVE JAKE LEHMAN AND CARISSA GUST, GO OR G GEO GUST.

OKAY, WE'RE HERE TO REVIEW, UH, TO LOOK AT THESE SUBMISSION MADE FOR TWO 80 NORTH CENTRAL AVENUE, HARTSDALE, NEW YORK.

THE FIRST SUBMISSION WAS MADE ON THE 10TH OF APRIL, 2025 AND REVIEWED AT OUR FIRST MEETING, WHICH WAS THE FIF 15TH OF APRIL, FIVE DAYS LATER.

THE SECOND SUBMISSION WAS MADE ON THE 13TH OF AUGUST, 2025.

AND IT WAS REVIEWED SIX DAYS LATER ON THE 19TH OF AUGUST, 2025.

THE THIRD SUBMISSION WAS MADE ON THE 10TH OF NOVEMBER, 2025.

WE SCHEDULED A MEETING FOR THE 14TH OF NOVEMBER, 2025, BUT THE APPLICANT, UH, REQUESTED THAT WE CHANGE THE DATE OF THAT MEETING.

SO THE STOP CLOCK STOPPED, WHICH WAS FOUR DAYS, AND THE MEETING WAS HELD ON THE 18TH OF NOVEMBER, 2025.

WE JUST RECEIVED THIS SUBMISSION.

UM, IN EACH OF THOSE INSTANCES, THE APPLICATION WAS DEEMED INCOMPLETE.

WE JUST RECEIVED THE SUBMISSION ON THE 13TH OF JANUARY, 2026.

TODAY IS THE 16TH OF JANUARY, 2026.

SO IT'S THREE DAYS LATER.

THIS IS AS MENTIONED FOR TWO 80 NORTH CENTRAL AVENUE, HEART STONE, NEW YORK FOR AT AND T AND LET'S GET STARTED.

NOW, WHY IS, WHY DOES IT SIGN? OH, YOU TOOK THE WRONG ONE.

YOU THE SEVEN ME .

OKAY.

AND HERE WE ARE.

OH, OKAY.

SO IN REVIEW, PLEASE STOP ME IF YOU HAVE A QUESTION.

SURE.

AND STOP ME IF YOU GUYS DON'T AGREE WITH WHAT I, I MIGHT, IN MY VIEW OF WHAT THE SITUATION IS, UM, WE HAD DEEMED ONE INCOMPLETE LAST TIME.

AND WHAT WE HAD WRITTEN WAS, UM, WHAT ITEMS IN THE REPORT ARE, ARE THE SPECIFIC INDIVIDUALS ATTESTING TO, AND THAT WE NEEDED EMILY'S QUALIFICATIONS IN THE RESPONSE SUBMITTED.

NOW THEY HAVE IDENTIFIED WHAT THE, WHAT IS BEING ATTESTED TO, AND THEY HAVE INCLUDED EMILY MCPHERSON'S, UH, LICENSE NUMBER, WHICH SHOWS US THAT YOU CAN INDEED HAVE AN RF ENGINEERING LICENSE NUMBER.

UH, IT, IT'S, IT'S A PROFESSIONAL ENGINEERING LICENSE NUMBER STILL.

THAT'S OKAY.

, THAT WAS JUST IN A SUMMARY TO POINT THAT SOMEONE ELSE CLAIMED THEY COULDN'T HAVE ONE.

OKAY.

AND HER, UM, WHAT SHE'S ATTESTING TO IS ACTUALLY ON THE NEXT PAGE.

YES.

YES.

UM, SO THAT IS, IN MY OPINION, NOW COMPLETE.

YOU'LL GET COPY OF THIS AND I'LL GO UPSTAIRS, I'LL GET IT STAMPED AND THEN I'LL PRESENT YOU WITH, PAUSE THE RECORDING.

I'LL GO UPSTAIRS.

YOU GUYS WILL TALK ABOUT ME WHILE I'M GONE.

AND, UM, WHAT'S AN EGO? YOU GOTTA GO WITH IT.

AND THEN I WILL, WE WILL START THE RECORDING AGAIN, AND I WILL PRESENT YOU WITH THE STAMP DOCUMENT FROM TIFFANY.

SO ONE IS NOW COMPLETE.

B, WE HAD DETERMINED THAT B, C AND D WERE COMPLETE LAST TIME AS WAS B AND A.

BUT THERE'S A SMALL PROBLEM.

WE HAD ASKED FOR SOME CHANGES IN F SO IT WAS A, IF YOU KNOW, AND YOU DID MAKE THE CHANGES, YOU JUST MADE ONE MISTAKE, WHICH IS

[00:05:01]

YOU WROTE THAT IT IS, IF WE GO TO IT, YOU'LL SEE.

UM, AND THIS HAS TO BE CORRECT.

YOU DIRECT US AND SORRY FOR THE GLASSES SCREEN.

F YOU DIRECT US TO BI DID GET AN EMAIL FROM STEVE APOLOGIZING FOR NOT HAVING CHAT AND OFFERED TO COME AHEAD, BUT I TURNED DOWN THE OFFER.

I DOING IT.

IF YOU TURN TO B, UM, IT SAYS MOUNT VISCO.

IT'S MOUNT KISCO.

OH, GEEZ.

THAT, THAT WAS, UM, THEY, I GUESS THEY, UH, SO THIS NEEDS TO BE CORRECTED.

SO IT REFLECTS THAT IT'S MOUNT KISCO.

YOU DID PUT IN THE PERSON WHO'S GAVE IT A NAME, YOU HAVE THE PERSON SIGNED, THE OTHER THINGS WERE CORRECTED.

THE DATE OF THE NOTARIES AFTER NOTARY DOING THIS, IT ALSO FITS WITH IT.

UM, SO, AND, AND UH, CAN I, YEAH.

IF I GO IN AND JUST HANDWRITING MYSELF AND JUST THEN, UH, INITIAL IT, WOULD THAT, WOULD THAT WORK? I KNOW IT'S NOTARIZED A NOTARIZED DOCUMENT, BUT WE ARE BEING RECORDED.

SO , I DON'T THINK YOU COULD CHANGE THE NOTARIZED DOCUMENT.

NO.

OKAY.

UNLESS THE NOTARIZED, I JUST FIGURED FOR LIKE A MINOR, A MINOR, LIKE THAT MINOR IS ALWAYS A VERY SUBJECTIVE CONCEPT.

OKAY.

SO IT'S AN OFFICIAL DOCUMENT, BUT IT'S A HIGHER STANDARD WHEN IT'S NOTARIZED.

UNDERSTOOD.

FEE.

SO WE NEED, IT WAS MOUNT KISCO WITH A K.

YEAH.

AND IF YOU LOOK BACK AT YOUR LAST DOCUMENT, THAT'S HOW I KNEW IT WAS SUPPOSED TO BE.

'CAUSE I WENT AND LOOKED AT THE LAST NOTARY STATE.

IT WAS, IT WAS FROM MOUNT KISCO.

OKAY.

AND I JUST WROTE MATT KISCO.

I'M HOPING THAT WAS CORRECT, BUT IT MADE SENSE THAT IT WAS OKAY.

AND I KNOW THAT BEFORE THE MEETING STARTED, UH, YOU SAID IT DEPENDS ON HOW MANY ARE INCOMPLETE, RIGHT? WE, WE'LL SEE IF I, IF WE'LL SEE WHERE WE ARE IN THE END.

PERFECT.

OKAY.

UM, SO A DESCRIPTIVE G WAS A DESCRIPTION OF ALL WORK NECESSARY TO COMPLETE INCLUDING, UM, INCLUDING CONSTRUCT, CONSTRUCT AND INSTALL THE PROPOSED MODIFICATIONS, INCLUDING ANY NECESSARY EXCAVATION.

AND THEY, THEY GAVE US A VERY GOOD DETAILED CONSTRUCTION SCHEDULE HERE.

BUT THERE'S A PROBLEM, WHEN I WENT TO THE DRAWINGS IN ONE OF OUR VERY, FROM OUR MEETING ON THE 19TH OF AUGUST, WE ASKED YOU TO REMOVE THE TERM GROUND LEVEL FROM THE DRAWINGS MM-HMM .

AND IF YOU GO TO, OH, THE OTHER THING IS YOU SEND US TO T OH ONE SHEET T OH ONE, PLEASE SEE THE COVER SHEET, UM, FOR A DESCRIPTION OF WORK NECESSARY.

IT ACTUALLY DOESN'T HAVE IT THERE.

UH, IT WOULD BE THE, UH, THE PROJECT SCOPE, WHICH IS SO MUCH LESS THAN THIS.

RIGHT.

WE HAVE TO MATCH ALSO.

THEY SHOULD MATCH.

YEAH.

BECAUSE IT'S WHERE THEY'RE 2D THERE.

THIS, WE'RE ASKING FOR EVERY, THE WHOLE GOAL IS TO FIND OUT EVERYTHING YOU'RE SUPPOSED TO BE DOING.

YOU GIVE US THE SCHEDULE HERE, WHICH IS RE YOU COULD REPRODUCE IN THAT LATER QUESTION, RIGHT? BUT WHAT HASN'T BEEN THERE BEFORE HAS BEEN THE MOVEMENT OF, OF, UH, THE REMOVAL OR USE, OR THAT'S WHY, WHERE WE GOT TO THE FACT THAT WHETHER OR NOT THE AT AND T ANTENNAS WOULD BE WORKING, AND YOU ADDED TO THIS AT AND T WILL NOT BE DECOMMISSIONED, WHICH WAS A QUESTION IN OUR LAST REVIEW.

RIGHT.

UM, SO THIS REVIEW IS GREAT.

IT SHOULD MATCH WHATEVER YOU'RE SENDING US TO.

SO YEAH.

SO WE, WE DID DETAIL IT A LITTLE BIT MORE, UM, IN SECTION G.

UM, AND, AND YOU KNOW, IF YOU LOOK AT THE WEEKLY SCHEDULE, IF WE DO SAY, UM, YOU KNOW, WE'RE REMOVING THE EXISTING, UH, EQUIPMENT FROM THE EXISTING LOCATION, EVERYTHING THAT'S BEING REMOVED, UH, FROM THE EXISTING LOCATION AND WHAT WE'RE INSTALLING, WHICH AGAIN, IT, IT IS JUST A, A MORE DETAILED VERSION OF WHAT'S .

WELL, THIS IS, THIS IS, TO ME, IT'S, IT ALWAYS SEEMED LIKE WHY DOESN'T SOMEONE JUST DETAIL WHAT THEY'RE DOING AND THEY'LL ANSWER THAT QUESTION.

UM, BUT WE MADE IT BROADER SO THAT PEOPLE COULD JUST SAY THEY'RE MOVE, REMOVING ALL THE WIRES, OR THEY'RE DOING THIS AND, AND MADE IT SO THAT WE HAD A LISTING OF WHAT WAS HAPPENING.

NOT NECESSARILY WHEN IT WAS HAPPENING, BUT YOU

[00:10:01]

COULD PUT THE SAME THING IN BOTH PLACES, IT WOULD WORK.

OKAY.

BUT WHAT I'M REFERRING TO IS, UP HERE YOU SAY, PLEASE SEE THE COVER PAGE, SHEET NUMBER T OH ONE OF THE ENCLOSED CONSTRUCTION DRAWINGS FOR A DESCRIPTION OF THE WORK NECESSARY TO COMPLETE THE PROPOSED INSTALLATION AS WELL AS DESCRIPTION FOUND IN EXHIBIT L.

BUT WHEN I WENT TO THE WORK, IT DID NOT DO WHAT WE WERE LOOKING FOR, WHICH WAS THE SPECIFICS OF WHAT YOU WERE GONNA REMOVE AND WHAT YOU WERE GONNA INSTALL.

OKAY.

SO THERE'S ONE MORE PROBLEM THOUGH.

YOU CAN ASK YOUR QUESTIONS.

, I, I GUESS I WAS GONNA ASK YOU, SO IF, IF I JUST, UH, ADD THE, UM, THAT, THAT JOB, UH, PROJECT DESCRIPTION ONTO THIS SECTION FOR THAT BE, JUST TAKE OUT THE REFERENCE OF THE PLAN NUMBER.

TAKE OUT THE REFERENCE OF THE PLAN, THE SHEET NUMBER ZERO ONE.

YEAH.

YOU DON'T HAVE TO INCLUDE THAT BECAUSE THAT CONFLICTS WITH THE ANSWER YOU PROVIDE BELOW.

WELL, OKAY.

WELL, I WOULD ARGUE THAT, THAT IT'S JUST A MORE DETAILED WEEKLY SCHEDULE.

YEAH.

BUT THAT'S WHAT WE WANT.

THE OTHER ONE IS NOT THE OTHER ONE'S JUST, IT'S WHAT YOU CONSIDER SCOPE OF THE WORK AND IT'S UPGRADING.

DOESN'T TELL US WHAT THAT MEANS.

UPGRADING IS NOT A TANGIBLE FOR US.

OKAY.

WHAT WE WANT ARE THE TANGIBLES THAT YOU'RE GOING TO BE DOING.

UNDERSTOOD.

SO, OKAY, SO THAT'S, SO JUST REMOVE THAT REFERENCE, REMOVE THE REFERENCE THAT SAYS SHEET NUMBER PO ONE, BECAUSE IT'S TELLING US TO GO THERE TO LOOK AT THE ANSWER TO THE QUESTION.

AND THAT'S NOT THE ANSWER TO THE QUESTION, .

OKAY.

SO IT WAS AS I, I GUESS I WAS, I DID THAT AS A REFERENCE.

UM, WHEN I WENT TO, WHEN I WAS LOOKING THROUGH THE DRAWINGS, I WENT TO A O2 AND BECAUSE IT, IT ALSO GIVES US A LIST OF WHAT YOU'RE GONNA DO.

AND I WAS TRYING TO RECONCILE, AND WHAT I NOTICED AT THE TOP WAS THAT IT STILL SAYS GROUND LEVEL.

OKAY.

AND THAT WAS A NOTATION WE GAVE YOU IN AUGUST THAT SAID, TH THIS ISN'T ON THE GROUND.

THIS IS ON A ROOF.

OKAY.

YEAH.

'CAUSE THAT IS, UM, THE STANDARD CURRENT GROUND.

WHAT, WHAT, WHAT WE REALLY MEAN IS THIS ELECTRICAL ROOM, IF YOU WILL.

UH, BUT OKAY.

BUT THIS IS, SO YOU ARE SAYING THIS IS NOT ON THE ROOF.

IT IT IS ON ON THE ROOF.

IT IS OR IS NOT? IT IS, YEAH.

SO GROUND LEVEL SAYS TO US GROUND RIGHT.

ROOF LEVEL MEANS, OKAY.

UH, JAY CARISSA, IF YOU GUYS CAN, UM, DO A SEARCH TO SEE WHERE ELSE IT MIGHT COME UP.

YEAH.

ALL RIGHT.

OKAY.

SO WE JUST HAVE TO REMOVE ON THAT, UH, PAGE A O2 OF THE CDS OF THE CONSTRUCTION DRAWINGS.

UM, REMOVE WHERE IT SAYS GROUND, IT SHOULD BE ROOF LEVEL AND IT SHOULD SAY ROOF LEVEL.

OKAY.

UH, ANOTHER CORRECTION IN THAT PARAGRAPH.

THE LAST SECOND TO LAST LINE READS.

THIS IS AN EXISTING SITE, SO THERE WILL BE NO EXCAVATION.

THAT IS NOT A GIVEN.

WHEN YOU HAVE AN EXISTING SITE, TAKE OUT THE WORD.

SO PUT A PERIOD CAPITALIZE, THERE WILL BE NO EXCAVATION.

WHAT OLD IS IT IN THE CONSTRUCTION SCHEDULE? IS THAT OKAY TO KEEP FOR THE NEXT ONE? YEAH.

OR THIS, THIS WORKS.

OKAY.

I JUST HAVE ONE, ONE QUESTION.

THE NOTE TO GROUND LEVEL, WHAT SHEET ARE YOU LOOKING AT? UM, A OH TWO.

YEAH.

AND I'M NOT SAYING THAT IT DOESN'T OCCUR ANYWHERE ELSE.

THAT'S WHAT CAUGHT MY EYE.

AND THAT WAS A CORRECTION GIVEN BACK IN AUGUST, SO, AH, OKAY.

OKAY.

THANK YOU.

I DIDN'T, I'M JUST TRYING TO FIND EXHIBIT L.

OH, EXHIBIT L WAS, OH, IS THE, UH, RIGHT SCOPE OF AWARD DOCUMENT? WHERE IS IT? 'CAUSE I GO TO K, UH, IT SHOULD BE THE LAST PAGE PERCENT.

NO, YOU GO TO K ALSO.

FRANCIS, CAN YOU JUST LOOK AT YOURS TO SEE IF YOU HAVE ANYTHING AFTER? K, IF, IF YOU DON'T MIND IF I CAN COME OVER.

THANK YOU.

NO, NO GOES.

I,

[00:15:02]

IT'S HERE.

IT'S, IT'S, UH, IT'S THE, THE, THE EXHIBIT BEFORE.

OKAY.

OKAY.

TYPICAL .

YES.

IT'S A NEW ALPHABET.

START OFF THAT.

SO THE EXHIBIT 4K IS J AND THAT'S STRUCTURAL.

YOU DON'T HAVE A, AN L BEFORE THAT? J AN L USING, THERE'S NOTHING ON K? NO, THERE'S NOTHING.

OKAY.

BUT YOU HAVE, LET'S JUST WORK WITH LK IS THE DRAWINGS.

OKAY.

OUCH.

SO IS THE REFERENCE THE L OR NOT K? NO, THE REFERENCE IS SUPPOSED TO BE THE L IT K IS THE DRAWINGS, I THINK.

BUT L WAS JUST MISPLACED IN, IN THAT PARAGRAPH.

SO I'M JUST NOW LOOKING FOR SOMEBODY FROM KINDERGARTEN.

NO, THESE DAYS, THAT'S PRE-K.

OH, THAT IS NOT EVEN FORGIVABLE.

YOU'RE .

IT'S TRUE.

THEY'RE DOING ALGEBRA IN KIND.

PETER, YOU KNOW WHY IT IS THE ROOFTOP , WHAT I'M LOOKING FOR IS ARE THERE ANY WIRES THAT ARE INDEPENDENT OF THE CONNECTION THAT NEED TO BE REFERENCED? UH, THAT MAY BE A, A QUESTION.

YEAH, THAT'S DEFINITELY A QUESTION FOR, UH, CARISSA.

JAKE? UM, I'M SORRY, DO YOU MIND REPEATING THAT NEXT QUESTION? SO, UM, I'M JUST GOING OVER THE L UM, AND, AND ALSO LOOKING AT THE WEEKS IN THE ANSWER.

AND ONE OF THE THINGS I'M ASKING IS, ARE THERE ANY INDEPENDENT CABLES, CONDUCTORS, ANYTHING THAT IS NOT LISTED HERE THAT SHOULD BE INCLUDED? THERE SHOULD NOT BE.

NO, I'M, I'M LOOKING AT IT RIGHT NOW.

UM, AND EVERYTHING IS INCLUDED, SO I WON'T FIND ANY CABLES OR ANYTHING EXTRANEOUS ON THE LANDS WHEN WE GET TO S UH, NO, THERE SHOULDN'T BE.

I MEAN, I'M LOOKING AT IT RIGHT NOW.

UM, AND I DON'T SEE THERE, THERE WOULDN'T BE REALLY.

UM, BUT, BUT I'M REVIEWING WE CAN, I DON'T KNOW IF YOU WANNA CONTINUE OR, BUT, BUT NO, WE, WE SHOULD BE CLEAR, AS LONG AS WE'RE WORKING ON REVISING SOME OF THIS LIKE GROUND AND, AND THE OTHER ASPECTS, IT WOULD BE THE TIME TO NAIL THIS.

YEAH.

SO YOU MENTIONED GROUND AND, UM, AND THEN CABLING.

UM, YEAH, AND JUST TO, TO GO BACK THERE, I, I HAVE REVIEWED THE SET OF CDS YOU GUYS ARE LOOKING AT.

IT LOOKS LIKE THAT'S THE ONLY MENTION OF GROUND LEVEL EQUIPMENT.

UM, IT IS JUST OUR EQUIPMENT PLATFORM.

SO WE CAN, UH, WE CAN REVISE THAT LANGUAGE THERE.

YOU DON'T WANNA GET RID OF ANY, ANY MENTION OF GROUND BECAUSE IT'S A PLACE AND PLANS WHERE THEY TALK ABOUT GROUND MEANING GROUND ELECTRICAL.

SO IT'S JUST GROUND LEVEL.

GROUND LEVEL, YEAH.

RIGHT.

[00:21:08]

I, NO, YOUR HONOR, CERTIFICATE OF COMPLETION, IT HAS MOUTH KISS KIDNEY, BUT THAT WAS DONE BY THE TOWN OF GREENBURG.

SO YOU'RE NOT RESPONSIBLE FOR THAT.

I, IT'S, IT'S WRITTEN SIGNED BY JOHN, RIGHT? YES.

NO COMMENT.

OKAY.

SO THEN, SO THAT'S INCOMPLETE.

AND WHAT I HAVE WRITTEN HERE IS REMOVE FIRST SENTENCE WITH SHEET T ZERO ONE, UM, TWO, MAKE LAST SENTENCE INTO TWO SENTENCES AND, AND REMOVE THE WORD.

SO THREE, REMOVE GROUND LEVEL FROM DRAWING A O2 REPLACED WITH, UH, ROOF LEVEL.

OKAY.

WE HAD DEEMED, WE HAD DEEMED H COMPLETE I COMPLETE J COMPLETE AND K COMPLETE BEFORE WE HAD DEEMED F AND M COMPLETE.

WE FOUND N INCOMPLETE LAST TIME.

THE CHART NOW DOES INCLUDE ALL THE ANTENNAS ON THE ROOF.

UM, IT HAS 10 T-MOBILE AND AT AND T.

WHAT I ASKED, UM, STEVE, AND HE ACTUALLY, I, I TOLD HIM THAT THIS WAS SOMETHING WE LEARNED FROM 1 77 EAST HARTSDALE.

WHEN ANTENNAS ARE PLACED LIKE THAT, THEY OFTEN HAVE A SPRAY TO THE, TO THE SIDES IN THE BACK, WHICH IS MUCH MORE CONCENTRATED.

UM, AND HE SAID HE WOULD REACH OUT TO THE TWO PEOPLE WHO WERE ON THE CALL TO GET MORE, YOU KNOW, TO HAVE THEM LOOK INTO IT.

BECAUSE JUST LIKE AT 1 77 WHEN THEY, AND I ENCOURAGED HIM TO ASK THE BUILDING DEPARTMENT FOR EAST CARDALE AVENUE, 1 77 EAST HARSDALE AVENUE IS AN APARTMENT BUILDING.

AND WHAT WE LEARNED FROM THAT, ALTHOUGH THEIR CHARTS WERE CONFUSING, IT DID SHOW HOW THE SPRAY FROM THE ROOF MOUNTED ANTENNAS WENT TO THE SIDE AND WERE MUCH MORE CONCENTRATED.

WE DON'T, WE ONLY HAVE HERE WHAT IS TO THE FRONT, UM, WHICH IS NORMALLY FROM A MONOPOLE.

SO WE NEED INFORMATION ABOUT WHAT THEY, THEY DO TO THE SIDES.

BECAUSE AS I EXPLAINED TO STEVE EARLIER, 1 77 EAST HARTSDALE PUT UP CHAINS, I WOULD'VE LIKED MARKINGS ON THE GROUND, UM, IN ADDITION, BUT WE ONLY GOT HALF OF OUR REQUEST, BUT IT WAS ALSO REQUIRED BY FEDERAL LAW THAT IT BE MARKED OUT ACCORDINGLY.

SO YOU COULD POINT OUT ALL THESE CONVERSATIONS YOU'RE TALKING ABOUT WERE HAD WHEN THERE WASN'T A QUORUM OF THE BOARD PRESENT.

CORRECT.

WHILE, WHILE WE WERE WAITING PATIENTLY IT COULD BE GOT HERE EARLY KNOW, AND MAKE IT SEEM LIKE THERE WAS A PRE-MEETING THERE WAS.

CORRECT.

THERE WAS NO PRE-MEETING.

I, I JUST, YEAH, CORRECT.

UM, SO I CAN ATTEST.

SO WE GUYS AT T HAS TO FOLLOW ALL FCC REGULATIONS.

SO IF ANY KIND OF MITIGATION WERE REQUIRED FOR EMISSIONS ISSUES ON THE ROOFTOP, UH, WE WOULD, WE WOULD KNOW THAT AT THIS POINT BASED ON THE REPORT THAT WAS RUN.

UM, SO I, I DON'T, I

[00:25:01]

GUESS I DON'T UNDERSTAND THE, THE QUESTION.

SO I, UH, AGAIN, I'M NOT AN RF ENGINEER EITHER.

UM, SO WE CAN TAKE IT BACK TO THE RF ENGINEER.

I KNOW THIS WASN'T, UM, IT, IT WASN'T A, AN ASK ON THE PREVIOUS APPLICATION.

SO WE CAN CERTAINLY AS A COURTESY, GET THE INFORMATION FROM OUR RF ENGINEER IN TERMS OF ANY SPILLAGE.

UM, I'M NOT FAMILIAR WITH THAT TERM.

UM, BUT I CAN SAY THAT OUR REPORTS ARE COMPREHENSIVE.

SO IT DOES TAKE INTO ACCOUNT ANY RF EXPOSURE, ANY RF MITIGATION THAT'S REQUIRED ON THE ROOFTOP.

UM, AND SO THIS, THE, THE REPORT THAT YOU HAVE WOULD BE COMPREHENSIVE OF THAT, WHETHER IT'S ON THE SIDE OF THE ANTENNAS, IN FRONT OF THE ANTENNAS, BEHIND THE ANTENNAS.

NO, IT'S NOT.

SHOW ME ANYTHING THAT SAYS TO A STATEMENT THAT SAYS THAT THERE IS NOTHING TO THE SIDE.

WHAT YOU'RE CONCERNED WITH IS WHERE YOU OVER OVERREACH IN, IN PUTTING SOMETHING UP, JUST LIKE THESE ANTENNAS ON 1 77 DALE AVENUE, WE NEED A STATEMENT FROM YOU IN WRITING EXACTLY HOW MUCH GOES TO THE RIGHT AND THE LEFT AND BEHIND.

THAT'S NOT NEGOTIABLE AND IT'S NOT DISCUSSING, YOU KNOW, YOU UNDERSTAND WHAT WE NEED.

I'VE DIRECTED HIM TO A AND I'LL DIRECT YOU TO ASK THE TOWN FOR THE REPORT FOR 1 77 EAST HARSDALE AVENUE, BECAUSE THAT IS WHAT IS REQUIRED.

IT SOUNDS LIKE YOU HAVE THE DATA, IT JUST NEEDS TO APPEAR THE DOCUMENT.

YEAH, AND, AND I GUESS I, I HAS A, HAS AN RF RADIO FREQUENCY PERSON REQUESTED THIS BECAUSE THIS IS THE INFORMATION, MAYBE IT'S NOT DELINEATED THE WAY THAT YOU WANNA SEE IT, BUT AGAIN, THESE, OUR RF ENGINEERS AND ALL RF ENGINEERS HAVE TO TAKE INTO ACCOUNT RF EXPOSURE ON THE ENTIRE ROOFTOP.

SO IT'S ON THE SIDES OF THE ANTENNAS, BEHIND THE ANTENNAS, IT'S, IT'S, YOU KNOW, IT'S, THEY CALCULATE EVERYWHERE ON THAT ROOFTOP.

UM, SO IF THERE WERE EXPOSURE ISSUES LEAKING TO THE SIDE, TO THE RIGHT OR THE LEFT OF THE ANTENNAS, THAT WOULD BE INCORPORATED.

SO, UM, PERHAPS IT'S JUST NOT DETAILED IN, IN A MANNER IN WHICH MAYBE MAKES IT, YOU KNOW, EASY TO, TO READ.

AND LIKE I SAID, WE CAN CERTAINLY AS A COURTESY GO BACK TO THE ENGINEER AND SEE IF WE CAN GET SOMETHING.

THIS IS NOT A, LET, LET ME, I'M OBJECTING TO THE WORD COURTESY.

OKAY? THIS IS NOT A CONCERN.

COURTESY.

IT IS A REQUIREMENT.

AND WHEN YOU WRITE A LIST THAT SAYS AT 10 FEET, 10, 20 FEET, 30 FEET, AND YOU GIVE US THE, UM, THE NEAR LEVELS AT THAT LEVEL, YOU'RE NOT TELLING ME AT WHAT DIRECTION.

SO, NO, WE NEED TO KNOW.

SO GO AHEAD.

I'M SORRY.

WE NEED TO KNOW TO THE RIGHT AND TO THE LEFT, YOU HAVE BROUGHT UP A REALLY IMPORTANT QUESTION.

NOW I'M GONNA ASK YOU TO DELINEATE EXACTLY TO WHAT, WHERE YOU'RE MEASURING THAT, UM, THE, THOSE 50 FEET, 10 FEET, BECAUSE YOU'VE RAISED A GOOD QUESTION.

WHAT IS IT BEHIND IT? ARE THOSE 10 FEET BEHIND IT OR THE 10 FEET IN FRONT TO THE GROUND? SO THAT, OKAY.

I I, SO THE, THE ASK IS UNDERSTOOD, UM, IN TERMS OF THIS NOT BEING A, A, A REQUEST PREVIOUSLY, UM, I THINK WE'RE ALL AWARE THAT 64 0 9 DOES NOT ALLOW ANY ADDITIONAL OR NEW ASKS TO COME ABOUT AFTER THE INITIAL.

UM, SO LIKE I, THAT, THAT'S WHERE WE'RE COMING IN AS A COURTESY.

IF, IF YOU'RE REQUIRING IT, WE'LL GO BACK.

STEVE CAN RUN TO THE BUILDING DEPARTMENT BEFORE HE LEAVES GREENBURG.

UM, HE CAN TRY TO GET THE, OR HE, HE CAN REQUEST, UM, ACTUALLY I'M NOT, I'M, I'M OBJECTING TO THAT.

IT SAYS THE CHART MUST BE PROVIDED, INCLUDING ALL ANTENNAS ON THE PROPERTY, DETAILING THE DISTANCE AND MAXIMUM OUTPUTS.

SO YOU DID NOT, YOU DID NOT ASK FOR ADDITIONAL CLARIFICATION OF THAT.

SO YOU CAN'T REALLY SAY THAT IT WASN'T ASKED BEFORE.

UH, WE OH, OKAY.

SO, SO WE'LL, UH, WE'LL REQUEST THE INFORMATION FROM THE, UM, BUILDING DEPARTMENT ON THIS OTHER SITE.

I DON'T BELIEVE THIS IS OUR SITE.

UM, BUT IF THE BUILDING DEPARTMENT IS, WHO HAS THE INFORMATION THAT'S NEEDS TO BE INCLUDED, WE'LL ASK FOR THAT ON 1 77 EAST HARTSDALE HAVE IS NOT YOUR, IT IS NOT YOUR SITE.

IT IS A COURTESY OF OURS TO PROVIDE YOU WITH AN EXAMPLE OF ANOTHER SITE THAT DID THIS.

I PRO THE, THIS WAS A EITHER T-MOBILE, IT WAS IN THE VILLAGE OR AN APARTMENT BUILDING, AND IT WAS AN EXAMPLE OF WHAT WE'RE LOOKING FOR TO PROVIDE ADDITIONAL INFORMATION.

OKAY.

YEAH.

IT SEEMS LIKE YOU HAVE THE DATA, YOU JUST HAVE TO PROVIDE IT.

YEAH, NO PROBLEM.

AND WAS THAT FOR, UH, FOR ONE AND ONE? THEY OVERLAP.

OKAY, GOT IT.

THEY OVERLAP.

UM,

[00:30:05]

IN THREE, THIS IS THE SAME AS BEFORE.

THE, THE, UM, IT NEED, THE ANSWER NEEDS TO SAY THAT IT WILL COMPLY.

IT JUST SAYS IT'S GONNA GIVE A REPORT.

OKAY.

THE, THE, UH, MONITORING PLAN FOR THE APPLICANT'S EQUIPMENT WILL, THAT WILL PROVIDE ANNUAL STATEMENTS VERIFYING THE RADIO FREQUENCY EMISSIONS DO NOT EXCEED THE APPLICABLE FC APPLICABLE FCC REGULATIONS.

IT SAYS A MONITORING PLAN PREPARED BY AT AND T IS ATTACHED AS AN EXHIBIT SHALL SUBMIT THE ABOVE MENTIONED REPORT ANNUALLY.

IT NEEDS THE REPORT NEEDS TO, THIS ANSWER NEEDS TO SAY THAT IT COMPLIES.

WE HAD THAT BEFORE IN THE, IN I CAN GET OUT THE LAST DOCUMENT.

IT'S JUST THE ADDING OF THE WORDS THAT IT COMPLIES TO THE, UH, MONITORING PLAN TO THIS, TO THE ANSWER TO THE QUESTION.

IT SAYS, A MONITORING PLAN BY SHALL BE SUBMITTED, THE ABOVE MONITOR MENTIONING AND, AND REPORT THAT SHOWS THE, THE SITE COMPLIES WITH, WHICH WAS THE SAME QUE REQUEST WE MADE LAST TIME.

IT DID REMOVE THE NON-INTERFERENCE.

OKAY.

SO JUST TO, JUST THAT I'M CLEAR FOR, FOR, UM, FOR SECTION N, UH, YOU'RE ASKING FOR A CHART THAT SHOWS THAT, UM, AN RF SPILLAGE, AS YOU MENTIONED, TO THE RIGHT, TO THE, TO THE LEFT AND TO THE BACK, UM, AND A PARAGRAPH THAT SAYS WHAT THE SPILLAGE IS I HAVE, I EXPECT IT WILL.

AND THIS IS JUST AN OPINION, NOT A SCIENTIFIC ANALYSIS THAT IT WILL NOT BE A PROBLEM.

BUT WE NEED IN WRITING WHAT THE PERCENTAGES ARE SURROUNDING IT.

WHAT YOU'RE LOOKING AT UPSTAIRS OR GETTING FROM THEM AND ASKING THEM TO FORWARD YOU VIA EMAIL IS THE IMAGERY THAT SHOWS HOW THEY DID IT.

I JUST THOUGHT IT WAS SIMPLER TO SEE IT, UM, BECAUSE IT SHOWS WHAT'S INCLUDED.

OKAY.

BECAUSE IT ALSO SHOWS WHERE IT WAS NOT OVER.

GOT IT.

ALSO IN THE N PARAGRAPH, UM, FOR ONE, YOU HAVE, UM, ROUNDED THE EXPOSURE TO 7.9.

IF YOU'RE GOING TO ROUND IT, THEN YOU HAVE TO ROUND IT UP BECAUSE IT'S 7.965, AS IS STATED IN THE PARAGRAPH BELOW.

OKAY.

[00:35:06]

APPEAL NOTE ON OUR LAST REVIEW WITH YOU.

RESET EDIT PAGE QUESTION TO BE SPECIFIC TO THE QUESTION.

MM-HMM .

I THOUGHT THAT WAS IN REFERENCE TO, UM, THE, IN, IN, UM, THE NAME INTERFERENCE, CORRECT? I'M SORRY.

SO JUST TO BE CLEAR, JUST ADD THE FACT THAT IT'S WE MARKED OH, COMPLETE LAST TIME, PLEASE.

FRANCIS, IF YOU CAN HELP US LOOK AT THIS ONE.

WE HAD NOTED THAT THE REGULAR MODIFIER SHOULD BE REMOVED.

AND THIS MUST INCLUDE WORDING THAT IT IS AN EVALUATION OF ALL AT THAT SITE NOISE P AND THAT IS ATTACHED AS H AS THE NOISE PROFILE.

WHAT'S THE HEADING? THE HEADING FOR P I'M SORRY, WHAT'S THE HEADING FOR P AND UH, THE NOISE STUDY.

THE NOISE STUDY.

SO I WAS LOOKING AT THE NOISE STUDY AND FOR THIS APPLICATION, IT DOESN'T MATTER BECAUSE YOU'RE USING THE, THE, UH, LOWER THRESHOLD FOR RESIDENTIAL, WHICH IS 65, WHERE YOU COULD GO TO 70 IF IT WHATNOT FOR RESIDENTIAL.

THE ONLY THING I'M NOTICING IS THAT YOU USED THE WORDING, UM, THIS, THE CONCLUSION AND THE SITE IS COMPLIANT WITH THE MUNICIPAL NOISE ORDINANCE AT ALL PROPERTY LINES THAT INTERFACE WITH ANY RESIDENTIAL THAT IT'S NOT ACTUALLY THE STANDARD.

THE STANDARD, WHICH YOU CORRECTLY PUT.

IT DOES, IT DOESN'T AFFECT THIS APPLICATION.

IT JUST, IF YOU DO HAVE ANOTHER ONE WHERE THERE'S A, UM, THERE'S NOT A RESIDENTIAL STRUCTURE, BUT IT'S A RESIDENTIAL DISTRICT.

MM-HMM .

YOU STILL HAVE TO COMPLY WITH THE LOWER STANDARD.

IN OTHER WORDS, 65.

DO YOU WANT ME TO NOTE THIS HERE? ALTHOUGH IT DOESN'T APPLY, HE CAN TAKE THAT REFERENCE FROM THE OTHER SEVEN.

YEAH, I'LL DO, DO YOU, DO YOU UNDERSTAND WHAT I'M SAYING? UH, YES.

SO WHEN YOU ACTUALLY CITE OUR ORDINANCE, UH, THREE 80 DASH SEVEN C, IT SAYS ANY UNREASONABLE INTRU UH, INTRUSIVE NOISE EXCEEDING 65 DBA AT ANY TIME WITHIN A RESIDENTIAL DISTRICT OR EXCEEDING 70 DBA WITHIN, UH, ANY OTHER DISTRICT BETWEEN THE HOURS OTHER THAN GOES ON THE HOURS.

UM, I JUST WANTED TO BE CLEAR THAT IF THERE'S NO RESIDENTIAL STRUCTURE ON THAT PROPERTY, IT STILL COUNTS.

OKAY.

UNDERSTOOD.

SO IT'S COMPLETE.

YEAH, IT IS COMPLETE.

BASICALLY THE CONCLUSION, JUST HAVE TO REWORD THE CONCLUSION MM-HMM .

YEAH.

FOR ANY OTHER SITE THAT, THAT IS NOT IN THE RESIDENTIAL, I UNDERSTAND.

I WOULD ACTUALLY PREFER YOU TO CHANGE IT IN THIS ONE SO THAT WE DON'T GET INTO A, IF SOMEBODY SAYS, YOU ACCEPTED IT, YOU ACCEPTED IT HERE.

OKAY.

SO HOW DO YOU WANT THAT WORDED? I'M GONNA SAY COMPLETE, CORRECT.

AND I'M GONNA UNDERLINE IT.

[00:40:04]

WE'RE GOOD.

I COULD SAY THE SITE IS THE PLAN WITH THE, UH, MUNICIPAL NOISE, OR I GUESS THAT'S GENERIC FOR OTHER MUNICIPALITIES.

MIGHT AS WELL SAY THE TOWN OF GREENBURG'S NOISE ORDINANCE, UM, PERIOD.

THAT SHOULD CONCLUDE.

BUT YOU, YOU DO ADDRESS THE DETAILS OF IT EARLIER.

SORRY IF I, I JUST COMBINED LIKE THAT.

PERFECT.

OKAY.

UH, AND YOU'RE SAYING THAT FOR THIS ONE WE SHOULD THAT, OR IS THIS I WOULD LIKE THAT TO TAKE OUT BECAUSE IT, YOU'RE PUTTING A CAVEAT THAT MAY NOT BE THERE.

UNDERSTOOD.

AND THE CAVEAT TO ZEBRA, THAT'S IN SECTION, UH, SIX OF THAT REPORT, THAT CONCLUSION.

OKAY.

DID YOU HAVE ANOTHER SEC? ANOTHER ASPECT ABOUT THAT SECTION SIX.

SO YOU WANTED TO STOP AFTER ORDINANCE, RIGHT? IT'S JUST A CONCLUSION OF THE, THE MAIN CUTS OF THE DOCUMENT PRECEDES THAT.

SO THEIR CONCLUSION IS IT'S , BUT THE GREEN, THEY WANNA ADD TO THAT CITED HEREIN BECAUSE YOU CITE THE ULAR NOISE ORDINANCE.

I THINK THAT WOULD BE GREAT.

WHAT I'VE WRITTEN IS CORRECT LANGUAGE PAGE ON PAGE FIVE OF THE NOISE REPORT 6.0 CONCLUSION.

REMOVE REST OF SENTENCE AFTER ORDINANCE IN THE FIRST SENTENCE.

THIS IS NECESSARY.

THIS IS BECAUSE THE REPORT PROCEEDS IT, BUT I THINK I MENTIONED, UM, THAT THEY, THE, UH, FIRST OF ALL THE, THE GREENBERG NOISE ORDINANCE AND ALSO THE, UH, CITED, CITED HERE, WHICH IS GONNA BE ANOTHER ONE.

I ASSUME YOU'RE GONNA USE THE SAME THING OF ALL THE DOCUMENTS CITED HERE.

SO ADD GREENBERG, NOT NECESSARY, BUT THE, THAT LAST PART, BUT IT WOULD SHOW THAT IT'S NOT JUST A PAGE TICKET FROM ANY REPORT THAT YOU DO FOR ANY MUNICIPALITY.

.

OH YEAH.

THE OTHER REPORTS THAT WE HAVE FOR THE OTHER SOUTHERN SITES, UM, ARE SPECIFIC TO THAT SIDE.

OKAY.

SO NOW I ADDED ADD GREENBERG TO SECTION SO THAT IT READS TOWN OF REED, AMERICAN NOISE ORDINANCE.

THAT'S, YES.

NOT ANOTHER CHAPTER CITED HERE.

THEY DO A GOOD JOB OF CITING

[00:45:01]

OR ORDINANCE.

SO EVERYBODY KNOWS WHAT IT'S ABOUT.

R IS COMPLETE FROM LAST TIME.

LET'S LOOK AT S TOGETHER.

OH, I BELIEVE WE SKIP Q UNLESS YOU, UM, OH, THIS ANSWERS, WHEN ARE THE TENS BEING REMOVED BEFORE THE DUNNAGE? THAT, THAT PARAGRAPH EXPLAINS IT.

UM, AGAIN, THE LAST LINE NEEDS TO BE CORRECTED IN THAT PARAGRAPH READS THERE, THIS, THERE'S AN EXISTING SITE THAT, SO THERE WILL BE NO EXCAVATION.

THAT'S A FALSE CONCLUSION.

SO WHAT IS EXISTING VERSUS NEW HAS BEEN ADDRESSED? THE QUESTION SAYS, WHEN AND WHERE ARE THE NEW ANTENNAS BEING INSTALLED? THAT'S ADDRESSED.

SO FOR ME, THIS IS COMPLETE.

R IS COMPLETE.

LET'S LOOK AT S NOW THIS DRAWING IS VERY CONFUSING.

MUCH

[00:50:01]

MORE THAN ANY I CAN EVER SEEN PEOPLE TO LOOK AT APPLICATION DONE BEFORE.

BETTER INK ONE STRONG.

YES.

NOTICE THE DATE THERE.

DOES THAT SAY IT EXPIRED ON THE 18TH OF DECEMBER? NO, THAT'S WHEN THEY UH, THAT'S WHEN THEY NOT AND SIGNED IT.

OKAY.

NOT CORRECT SIR.

SHOWING NOT BEING SEVEN 31ST IF YOU CORRECT.

YEAH.

ONE OF THE QUESTIONS I HAD NOTICED ON ONE OF FILLINGS ONE RIGHT THERE, BUT I HAVE WHAT ON A TWO.

A TWO.

IT SAYS, NOW WITH EXISTING PROPOSED LIGHTING IS INSTALLED AT THE, AT THREE PLATFORM, THAT DOESN'T ANSWER THE QUESTIONS THAT MAYBE IT DOES SOMEPLACE ELSE.

THAT NO LIGHTING WILL BE ON THE HOPE NO, NO LIGHTING EXISTS 'CAUSE IT IDENTIFIES THE PLATFORM AND I HAVE NO IDEA WHAT THAT MEANS TO BE.

SO WE NEED A STATEMENT THAT SAYS EITHER THERE WILL BE LIGHTING OR THERE'S EMERGENCY LIGHTING, OR THERE'S NO LIGHTING AT ALL.

NOT JUST ON THE PLATFORM, BUT ON THE .

IS THAT ANYWHERE IN HERE, STEVE? UH, I'M PRETTY SURE WE HAD HERE.

IT'S JUST A LINE.

THAT'S WHY IT'S HELPFUL TO HAVE THE OTHERS ON LINE AS WELL.

SO YEAH, THIS IS ON EVERYBODY.

YEAH.

SO I, I BELIEVE THAT LIGHTING IS EXISTING ON, ON THE SITE.

SO I I CAN ADD IN THE LINE THAT THAT STATES, THAT IS, DOES AT AND T HAVE LIGHTING OR NO LIGHTING AND WHERE IT IS? AND THAT'S SOMETHING WE NEED TO SEE ON THE DRAWINGS.

AND WHETHER IT IS JUST EMERGENCY LIGHTING OR WORK LIGHT.

THERE'S A NOTE ON 8 8 2, RIGHT? IT SAYS ON THE PLATFORM, BUT IT DOESN'T TELL US WHERE THE PLATFORM IS.

I MEAN, WHAT ABOUT THE REST OF THE SITE? IT'S VERY HARD.

IF YOU LOOK AT A OH THREE, I'VE NEVER SEEN .

THERE'S SO MANY LINES CONFUSING.

THE OTHER, UM, UM, YEAH, WE, WE TRIED MAKING IT AS DETAILED AS POSSIBLE.

UM, WE WENT, UH, WE ACTUALLY, WE GOT A COPY OF T-MOBILE'S, UM, PLANS AND, AND LIKE I SAID BEFORE THE CALL, WE DID TRY TO MIMIC THIS APPLICATION AS AS BEST.

UM, SO WHAT YOU SEE THERE IS, IS I DON'T RECALL THE SAME LINES OF THE BUILDING.

SEE THIS, THIS BECOMES AN OVER DIFFICULT OBJECTION.

WHAT IS THE I KNOW YOU CAN ASK HIM.

WHAT'S THE P-A-E-N-I-L-A PANEL? UM, NOT IF IT'S MISSPELLED.

OKAY.

OKAY.

I CAN, I CAN I TWO PAGE A TWO.

I WAS LOOKING THE WORD.

OH, THINKING IT'S A TECHNICAL .

I THOUGHT MAYBE

[00:55:01]

ON A O2, AS LONG AS WE'RE THERE.

WHAT ARE, WHAT ARE THESE LINES? A O2, THE, THE DOTTED LINE.

OH, WHAT IS IT? THE DOCTOR HERE? THIS, UH, THIS IS THE, UH, THE EXISTING AT T EQUIPMENT PLATFORM.

IT, UH, THIS, THIS, UH, RECTANGLE THAT YOU'RE LOOKING AT? YEAH, THIS IS IT IDENTIFIED SOMEPLACE THERE? YEAH.

UP HERE.

EXISTING ATT EQUIPMENT PLATFORM.

TALKING ABOUT THE DOTTED LINE.

NO, THAT'S THE NEXT QUESTION.

WHAT IS THE DOTTED LINE? THAT LIKE EXPANSION LINES OR SOMETHING? DOTED LINE USUALLY MEAN NOT SHINE SOMETHING.

ISSA OR JAKE, IF YOU GUYS, UH, CAN TAKE A LOOK AT THE CDS FOR PAGE A OH TWO.

UM, ON THE RIGHT HAND SIDE THERE'S A DOTTED LINE IF, UM, AND UNDERNEATH AND IT EXTENDS ABOVE.

AND WHAT WAS YOUR FIRST QUESTION? RECTANGLE.

WHAT? WHICH REC THE RECTANGLE? AND HE'S SAYING THE EXISTING AT AND T EQUIPMENT PLATFORM.

OF COURSE THAT DOESN'T TELL US FROM THIS, BUT THERE'S LOTS OF RECTANGLES.

WHICH ONE ARE YOU TALKING ABOUT HERE TO THIS LINE THAT I WAS ASKING ABOUT THIS LINE? YEAH.

WHAT IS HELPFUL WITH THIS THAT'S NOT HERE IS EVEN IF YOU WERE JUST TO PUT IN CENTRAL AVENUES HERE, SINCE WE KNOW WE, I SEE THIS COULD BE, I KNOW THAT YOU HAVE THIS, BUT IT'S ALSO NOT CLEAR HOW THE BUILDING SITS ON THAT FOR US.

MM-HMM .

AND STEVE, GOING BACK TO THE, UM, THE DOTTED LINE THAT WE WERE JUST TALKING ABOUT.

IT GENERALLY DELINEATES THE CABLE RUN, BUT I'LL HAVE TO DOUBLE CHECK WITH A AND E.

THAT'S WHAT THEY MEANT.

THERE IS A CABLE THAT I ASKED ABOUT THAT I DIDN'T SEE LISTED.

WAS THAT LISTED IN THE WORK BEING DONE? I APOLOGIZE.

COULD YOU REPEAT THAT? UM, WHEN WE WERE DISCUSSING WORK TO BE DONE, I ASKED IF THERE WERE ANY INDEPENDENT CABLES OR ANYTHING AND CARISSA SAID NO.

AND IF YOU'RE SAYING THAT'S A CABLE RUN, THEN THAT'S, IT SEEMS TO ME TO BE AN INDEPENDENT CABLE RUN.

YEAH, LIKE I SAID, I WOULD NEED TO DOUBLE CHECK WITH A AND E TO MAKE SURE THAT THAT IS WHAT THEY INTENDED BY THAT DOTTED LINE.

IF THAT IS A CABLE, WE NEED THAT CORRECT LISTED.

YES.

SO GETTING BACK TO THE FIND, IS THERE A PLACE MARKING ON THESE DRAWINGS WHERE THE SIGNAGE IS GOING TO GO? NOT ON THE DRAWINGS, BUT WE DO HAVE, OH, SORRY.

NO, THAT'S ALL I MISSED.

SORRY.

UH, YES.

TOWARDS THE BADGE, NOT THE PICTURES OF THOSE SIGN.

IT SAYS A PLAN ILLUSTRATING AND WE NEED TO KNOW WHERE THE SIGNAGE IS GONNA GO ON.

SO THE SIGNAGE WILL BE GOING ON THE INTERIOR SIDE OF THE DOOR.

SO WHERE DOOR, WHICH I DON'T RIGHT.

OKAY.

I SEE WHAT YOU'RE SAYING.

OKAY.

I CAN HAVE THAT LISTED.

SO YEAH, WE DID HAVE WANTED A PICTURE OF THAT HERE LONG AGO.

BACK IN 96.

WE AGREED THE PICTURES WERE NOT GOING TO, PICTURES ARE NOT WHAT WE GO BY.

MM-HMM .

BUT WE NEED TO SEE ON HERE WHERE THE DOOR IS, WHERE THE SIGN IS GONNA GO.

THOSE SITES ARE NAMED ARE ALWAYS, UH, FASCINATING.

ME.

ANY, ANY REASON WHY THIS SITE IS CALLED KENT OWNER? I

[01:00:01]

HAVE NO IDEA.

.

WE ACTUALLY ON, ON OUR END, UH, A ARIZONA, WE, WE HAVE IT NAMED AS, UH, PARKDALE.

THAT'S THE, THE NAME OF THE SITE.

SO I GUESS AT AND T CALLS IT, UM, YEAH.

HAVE IT'S IN WE ARE, BUT THIS, THIS ONE SPECIFICALLY IS IN HARTSDALE AND THE, AND THE SAME PLACE WHERE YOU'RE LOOKING AT THE WESTCHESTER COUNTY.

THAT SPACE BETWEEN BUILDING AND COUNTIES IS NOT SUPPOSED TO SAY THAT THIS IS OWNED BY THE COUNTY.

'CAUSE IT'S NOT.

UH, YEAH.

WHERE THAT, YEAH.

IT'S KIND OF WEIRD THAT THEY DO THAT.

THINK .

OH WELL, OKAY.

NO, THAT, YEAH, WE, THAT'S JUST THE ADDRESS AND, AND HARTSDALE IS IN WESTCHESTER COUNT COUNTY THAT, BUT THAT'S WHAT'S BUILDING COMING THERE.

THAT'S JUST REFERENCING THAT THIS IS THE BUILDING.

OKAY.

ON THE DRAWING, I THINK, YEAH, I THINK THAT SPACE HERE, JUST, UH, THOSE THAT IT'S, THIS IS THE ADDRESS AND THAT'S JUST WHAT IT IS.

A BUILDING MORE THAN A BUILDING IT SENT, UH, I WOULD JUST REMOVE THAT.

I DON'T KNOW WHY YOU HAVE THAT THERE BECAUSE IT DOES LOOK LIKE WESTCHESTER COUNTY.

THAT PARTICULARLY SINCE THAT MAKES NO SENSE.

IT'S UM, WHAT ARE, WHAT ARE THE OTHER SHEETS ON BUILDING? YEAH, I THINK THEY'RE ELEVATED.

I THINK IT'S PROBABLY INTENDED TO DIFFERENTIATE BETWEEN MONOPOLE OR SOMETHING ELSE, BUT IT DOESN'T, IT GETS CONFUSING.

OKAY.

SO JUST REMOVE THE WORK FOR US.

WE DON'T NEED ON THE FRONTIER.

YOU SAY SITE TYPE BUILDING.

SO WHY DON'T YOU SAY SITE TYPE AND BUILDING THERE OR NOT PUT IT AT ALL BECAUSE YOU HAVE SITE, YOU HAVE BUILDING ON THE TITLE SHEET, BUT THE TITLE SHEET IS CLEARLY NOT ABOUT THE BUILDING, IT'S ABOUT THE VICINITY.

MAIN THING IS WE DON'T WANNA MAKE THIS SEEM LIKE IT'S A GOVERNMENT BUILDING.

SO WHAT WOULD BE THE OTHER SITE TYPES THAT YOU USE? WELL, LIKE, LIKE YOU SAID, A MONOPOLE, A GUIDE TOWER.

UM, YEAH, YOU DON'T DO ANY GROUND MOUNTS, I ASSUME BECAUSE THAT WOULDN'T, THAT WOULDN'T GET THERE.

I SIGNAL OUT TO A RIGHT.

SO BUILDING LEY POLE BASICALLY.

YEAH.

THERE, THERE'S A FEW THAT, THAT, RIGHT.

OKAY.

YEAH.

SO TO ANSWER YOUR QUESTION, NO, TYPICALLY AT AND T WON'T PUT ANTENNAS ON THE, ON THE GROUND.

THEY'RE NOT GONNA EMIT ENOUGH, UM, SERVICE.

BUT WE DO, WE DO WATER TANKS, MONOPOLES, MONO PINES, UH, UTILITY TOWERS, ROOFTOPS.

SO ARE YOU, ARE YOU WITH AEROSMITH OR ARE YOU WITH AT AND T? ISSA.

AEROSMITH.

YEAH.

I'VE WORKED FOR AT T FOR A LONG TIME THOUGH, SO ON THEIR BEHALF, BUT MAYBE JUST MAKE SITE TYPE THE BUILDING.

OF COURSE.

YEAH.

YEAH.

WE'LL DEFINITELY CHANGE THAT TO, TO PROVIDE SOME MORE CLARITY THERE.

OKAY.

WE HAVE LOTS OF PROBLEMS WITH THE DRAWING, SO LET'S HAVE PHYSIO ON THOSE.

UM, HERE IT SAYS EXISTING AT AND T EQUIPMENT, UM, PLATFORM.

I WENT BACK TO SEE IF THE, THERE IS NO TO PLEASE STEVE.

TELL ME IF YOU SEE A LINE FOR WHERE IT TELLS ME THE HEIGHT OF THAT, UH, THE LINE FOR THE AT T EQUIPMENT PLATFORM.

OH, FOR THE PLATFORM? NO, WE HAVE THE, UH, THE HEIGHT OF THE, OF THE INTENTS.

WE NEED THE HEIGHT OF EVERYTHING, THE AS WELL WITH, AND NOT JUST THE PLATFORM, EVERYTHING THAT IS OUT THERE.

OKAY.

THAT'S WHY THESE LINES GET VERY CONFUSING AND VERY HARD.

WHY SOMETIMES DRAWINGS HAVE THEM IN OTHER COLORS.

WHY THEY DO THEM IN DASHES.

WHY THEY DO THEM IN DIFFERENT WAYS? BECAUSE WHEN WE START, IF YOU LOOK AT THE BUILDING, SOMEONE DOES PUT ON THE BUILDING, INSTEAD OF JUST DOING THE OUTSIDE, THEY PUT IN , RIGHT.

CROSS HATCH, WHICH MAKES IT MUCH MORE DIFFICULT TO SEE WHERE THE LINES HAVE MM-HMM .

SO EVERYTHING ON THAT BUILDING COUNT, INCLUDING THE EXISTING .

WE NEED HEIGHT OF EVERYTHING.

WE NEED THE HEIGHT OF THE EXISTING ELEVATOR PLATFORM WITH HAND DRIVES.

OKAY.

AGAIN, YOU HAVE AN INFORMATION BECAUSE OTHERWISE THE ENGINEER OR

[01:05:01]

THE ARCHITECT WHO DID THIS WOULDN'T BE ABLE TO DRAW IT.

SO, AND, AND THIS IS JUST A QUESTION FOR, FOR MY UNDERSTANDING.

UM, WHY, WHY EXACTLY DO WE NEED, UH, THE HEIGHT OF EVERYTHING EXPLAINED IN THE APPLICATION? BUT IF YOU GO BACK AND YOU READ, IT EXPLAINS IN THE APPLICATION QUESTIONS FOR ALL OF THIS, WHERE IS THE COLOR ON HERE? THE, I'M SORRY, THE COLOR.

MM-HMM .

EVERYTHING'S SUPPOSED TO BE ON THE DRAWINGS AS WELL.

SO YOU HAVE OH, THE COLOR.

UH, YES, THE COLOR IS, THAT WAS A POINT THAT WE MADE, BUT UH, THE COLOR IS RIGHT BACK COLOR LIKE RED.

THAT WAS THE PREVIOUSLY TAKEN, COULD, COULD SOMEBODY EXPLAIN WHAT A WARM ROOFTOP IS? I HAVEN'T SEEN THAT TERM.

NICE.

AO THREE SWAP METHOD IS WARM ROOF.

YEAH, I CAN TALK TO THAT A BIT.

IT'S MORE SO FOR THE GENERAL CONTRACTOR, JUST TO DELINEATE SHOULD BE CONSTRUCTED WHETHER SECTOR BY SECTOR, IF ALL SHOULD BE TURNED OFF AT ONCE.

SO DOES THAT MEAN MORE MEANS THAT SOME WILL BE ON WHILE OTHERS ARE BEING WORKED ON? YEAH, IT'LL, IT MEANS IT'LL BE DONE SECTOR BY SECTOR.

SO IS THERE SUCH A THING AS A COLD ROOFTOP, MEANING EVERYTHING GETS SHUT DOWN AT ONE TIME? YES.

AND THEN VICE VERSA? THERE'S A THANK YOU.

NO.

SO DO YOU WANT ANYTHING CHANGED ON THAT, FRANCIS? NO.

WHERE IS THE DOOR DELINEATED ON THESE DRAWINGS? IT SO I, I DID NOT SEE IT BEFORE.

I BELIEVE IT MIGHT BE, OH, HERE IT'S, OH ACTUALLY NO, IT'S NOT ON.

YEAH, SO I, I I ACTUALLY DON'T THINK WE NEED A DRAWING THAT SHOWS US EVERYTHING.

SO JUST BECAUSE I THOUGHT TO ASK ABOUT THE DOOR MAKES ME WONDER WHAT ELSE IS NOT ON HERE.

OKAY.

THE DRAWING MUST INCLUDE EVERYTHING.

OKAY.

[01:10:06]

YEAH.

SORRY MORE.

NO, THAT'S OKAY.

THAT'S OKAY.

OH, I'M ACTUALLY, UH, I BELIEVE IT'S ON A, SO I IMAGINE YOU'RE GONNA NEED IT ON PAGE A OH THREE AS WELL, BUT THE DOOR WILL BE FALL OUT ON PAGE A, THE DOOR BE RIGHT THERE.

IT'S, UH, MORE DOOR WHERE THAT, THAT'S ALSO A, ANOTHER DOOR THAT'S STILL THE OPPOSITE SIDE.

UH, YOU WANT NO, I SEE IT.

THIS ACTUALLY CORRECTS THE PROBLEM, NOT OF THE HEIGHTS, BUT IT CORRECTS THE PROBLEM OF THE SIGNAGE WITH THE EXCEPTION THAT IT POINTS AT THE EXTERIOR OF THE DOOR.

AND I BELIEVE YOUR SIGN IS GOING ON THE INTERIOR, SO YOU NEED TO CLARIFY WHERE IT'S GOING, BUT BECAUSE YOU, IT'S HARD TO SHOW ALL THE THINGS ON THE OTHER DRAWING.

SOMETIMES YOU NEED TWO DRAWINGS FROM ABOVE TO SHOW WHERE THE DOOR IS.

BUT IT DOESN'T STOP THE FACT THAT WE NEED HEIGHTS OF ALL OF THESE THINGS.

THAT WOULD BE ON PAGE A OR A OH THREE.

UH, SO WOULD, WOULD, WOULD YOU BE OKAY WITH US ADDING THE HEIGHTS TO THIS PAGE? NO, BECAUSE IT, IT MAKES THE PURPOSE IS TO SEE WHAT, HOW THE DIMENSIONAL CHANGE.

RIGHT.

MAKES SENSE.

OKAY.

I WAS JUST ASKING IF THIS HAVE A SECOND DOOR.

YOU NEED TO SIGN ON THAT DOOR AND WE'LL LEAVE DOWN.

THERE'S A SECOND DOOR THERE.

THE SECOND.

YEP.

IT, IT NEEDS TO BE IDENTIFIED, RIGHT? AND AN ARROW DOOR.

SO WHERE IT SAYS EXISTING AT T SIGNAGE, WE WOULD JUST ADD AN EXTRA, EXTRA FEW WORDS THAT SAY ON THE INTERIOR SIGN OF THE BUILDING.

OKAY.

WITH THE RIGHT SIGN.

IF IT'S GONNA BE ON THE INTERIOR OF BOTH DOORS, RIGHT.

CONFIRM THAT.

NOT SURE THE YEAH.

IS IS THAT REQUIRED? YES.

THE GOAL IS TO KEEP PEOPLE FROM OPENING THE DOOR ONTO THE ROOF IF THEY DON'T SEE AS THEY CAN DO.

THE GOAL IS TO KEEP PREGNANT WOMEN FROM GOING OUT ONTO THE ROOF.

ABSOLUTELY.

PEOPLE WHO WANNA SMOKE THEIR CIGARETTES SHOULD KNOW THAT.

WELL, THEY SHOULD KNOW THAT THAT'S THEIR CHOICE.

IF THEY'RE READING THEM ON THE OUTSIDE OF THE DOOR, BECAUSE THEY PROBABLY CAN'T EVEN LOOK AT IT WHEN THE DOOR CLOSED, THEN THEY CAN BE BACK.

IF THEY SAID, OH BY THE WAY, THE INSIDE OF THE DOOR, UH, SINCE THESE DRAWINGS ARE ARE, UH, GARBAGE, WOULD IT BE OKAY IF I TAKE A SET AND AND WRITE NOTES ON THEM BEFORE, BEFORE I LEAVE? YOU KNOW WHAT? WHY DON'T YOU TAKE THEM FROM, DO YOU HAVE DONNA? UM, I PUT IT OVER THERE.

YES, UNDER THERE.

FRANCIS.

IT'S A BLACK BINDER.

PUT IT OVER THERE.

NO, YOU HELD IT.

IT SAID DONNA.

OH, DONNA.

AND THIS ONE SAID DONNA.

NO, THAT'S JUST DIANE.

NO, I TOOK HER NAME AND CALLED.

OH, .

.

THERE SHOULD BE ANOTHER ONE FOR HER.

IT, YEAH.

MARK.

MARK.

YEAH.

WELL IT, BUT IT'S EASIER I THINK WHEN, LET'S MAKE, LET'S FIND WHERE IT'S GOING.

CAN'T BE, I DON'T THINK THIS IS CONFUSING TO MAKE

[01:15:01]

YOU LOOK AT AT, YOU HAVE SAID IT SAYS EXISTING AT T EQUIPMENT PLATFORM AND THAT WOULD BE THIS AND THIS LINE POINTS TO THIS BROKEN LINE.

MM-HMM .

SO WHICH IS IT THE INSIDE OR THAT, WHAT IS THE, YOU SEE THE QUESTION? THESE ARE HERE, THIS RECTANGLE IS IDENTIFIED AS AN INTENT EXISTING AT T .

RIGHT? RIGHT.

BUT IF I GO TO THIS, IT'S THIS BROADER EXISTING, I I THINK THEY'RE JUST, UH, THEY PUT THAT DOTTED LINE AROUND JUST A SHOW.

THE ARROW SHOULD REALLY LEAD TO WHAT IT'S REFERRING TO.

RIGHT? HEY GRAHAM, HERE I'M ON A ONE A OH ONE.

AND MY QUESTION IS, BECAUSE WE JUST WENT THROUGH THIS WITH THE CHECK THE DOTTED LINE ON THE OTHER, WHICH GOES AROUND THE BOX ON ONE SIDE, THEN WE HAVE A ANOTHER CHECK, UH, LINE THAT GOES AROUND HERE AND IT SAYS EXISTING 18 T EQUIPMENT PLATFORM AND IT SAYS CO2.

SO YOU GO TO A TWO AND THE PLATFORM IS NOT THAT EXTERIOR LINE.

THE PLATFORM IS.

NO I, RIGHT.

SO I THINK THAT THAT OVAL, IF JUST TO SHOW WHAT IS BEING SHOWN THEM CA TWO, THEN THEY SHOULD TAKE THE ARROW IN, TAKE THE ARROW INTO THE PLATFORM.

THE PLATFORM.

OKAY, I SEE WHAT YOU'RE SAYING.

SEE OR IN THAT, IN THIS CASE, WAIT, WE ARE ON A ONE.

SEE HOW THIS GOES HERE.

RIGHT? AND NOW THIS IS THIS RECTANGLE IN THE MIDDLE.

SO I'M SAYING IF BY LEAVING IT HERE INSTEAD OF TAKING IT TO HERE, I THINK THAT THEY'VE GOT MORE BROKEN.

BUT I DO THINK THAT STANDARD WAY OF, LET'S CALL IT, A LOT OF, A LOT OF THESE WE ARE, UM, STANDARD DON'T, DON'T, A LOT OF THE THINGS ARE INCOMPLETE.

SO I WOULDN'T GO TO ONE THING WITH FRANCIS PO STANDARDS A PROBABLY DIFFERENT THING LIKE THAT.

AN APP OF VS THIS PLAN SHALL INCLUDE A DESCRIPTION OF THE ANTENNA AND ALL RELATED STRUCTURES, FIXTURES, STRUCTURES OR PERCES AND APPARATUS INCLUDING HEIGHT ABOVE UNDISTURBED GRADE, ELEVATION ABOVE GRADE AND SEA LEVEL AND MATERIALS.

WE HAVE THE COLOR COVERED, THE SIGNAGE WE'RE MISSING AND LIGHTING WE'RE MISSING IN ADDITION TO THE HEIGHT.

SO WHAT I HAVE WRITTEN, MAY I INTERJECT FOR ONE MOMENT? YES.

CAN WE CLARIFY, UH, WHAT HEIGHTS WE STILL NEED SHOWN ON THESE DRAWINGS? EVERYTHING THAT DOESN'T HAVE A HEIGHT, BECAUSE THERE'S A LOT, IT'S LIKE THE EXISTING BULKHEAD.

THERE'S LOTS OF THINGS.

AND AS I EXPLAINED, AS I SAID TO STEVE, READ THE EXPLANATION OF WHY WE NEED IT.

WE HAVE SAID ON THIS, IT SAYS IT OVER AND OVER AGAIN ALL.

SO, SO IF YOU AND I UNDERSTAND THAT RESPECTFULLY, I, I I UNDERSTAND WHY IT'S REQUIRED.

I SHOW WE HAVE A HEIGHT OF THE EXISTING BULKHEAD.

THE ONLY THING I'M SEEING THAT WE DON'T HAVE A HEIGHT ON IS THE EXISTING PLATFORM WITH HANDRAIL.

AND I AM REFERENCING T-MOBILE'S EXISTING BULK.

WHERE IS THE EXISTING BULKHEAD? IT'S, IT'S ON THE OTHER SIDE.

OKAY, I JUST SAW IT TOO.

ON PAGE.

YEAH.

UH, PAGE A OH THREE AND YOU HAVE THE, YOU THE CHIMNEY.

YES MA'AM.

YEAH, YOU HAVE THE DOOR AND THE, THE TRUCK THROUGH THAT.

'CAUSE I'M NOT SEEING THAT HERE EITHER.

A OH FOUR OH WAS RIGHT.

MM-HMM.

A OH THREE, IT'S GONNA HAVE THE HEIGHT OF THE EXISTING ROOF, THE PARA PITT, THE BULKHEAD, UH, THE EXISTING CHIMNEY THERE, T-MOBILE'S EQUIPMENT, UM, ALL THE PROPOSED

[01:20:01]

AT AND T EQUIPMENT.

SO THOSE HAVE THE BULKHEAD POCKET.

IT DOES.

I'M SEEING THAT IT DOES.

YEAH.

SORRY, I I BELIEVE WE'RE MISSING THE, UM, THE DOOR, THE, UM, THE PLATFORM WITH THE HANDRAIL.

WHAT, WHERE EXISTING AT AND T TO BE REMOVED.

WHERE'S THE HEAD ON THAT? IT, IT WOULD BE THE, THE SAME HEIGHT.

WHERE AM I SEEING THAT? WHERE DOES IT CONNECT TO THE IT TENDS TO BE REMOVED.

THE RHI THINK IT'S HERE.

IT WAS AT TR AS PROPOSED SYSTEM.

OKAY.

SO, SO WE ALSO NEED THE HEIGHT OF THE EXISTING EQUIPMENT.

YEAH.

EVERYTHING HERE IS PROPOSED OR ACTUALLY IT EXISTS TO BE REMOVED INTO PANELS T PANEL.

THEY DON'T HAVE THE R RHS.

WHAT DO YOU NEED ME TO WRITE? SO THAT IS, SO THAT WE DON'T HAVE THIS CONVERSATION.

I WAS ACTUALLY GONNA ASK IF, UM, IF AFTER THIS CALL, IF WE COULD JUST SIT DOWN FOR LIKE 10 MINUTES AND, AND ALL ALL DEPENDS WHEN WE'RE DONE BECAUSE WE ALL HAVE LIES.

I UNDERSTAND.

NOT HAVE APPOINTMENTS, HAVE MEETINGS, HAVE BUSINESS.

RIGHT.

SO, UM, UM, I GUESS WE CAN I, YOU MARCO ON, ON MY, I I NEED TO WRITE IT ON HERE.

SO I NEED TO KNOW WHAT IS UNCLEAR.

SO WE NEED HELLO .

UM, WHO'S THE CHAIR OF THE .

I REGRET TO HAND THIS TO YOU MADAM CHAIR AND FOR THIS THANK YOU.

YOU'RE WELCOME.

ALSO, I'LL SEND IT TO YOU AND THEN THE EMAIL AS WELL.

OKAY.

THANK YOU.

WHERE DOES THE AIR SCALE MATCH UP TO SOMETHING CALLED THE AIR SCALE HERE? UH, THE AIR SCALE DUAL RH FOUR T, CORRECT.

FOUR R.

WHERE DOES IT MATCH UP TO? SOMETHING CALLED THAT ON THE SIDE.

ON THE SIDE.

OKAY.

SO THAT'S, THAT'S WHAT I WAS ALSO POINTING OUT.

UM, SO THAT, THAT NEEDS TO BE ANOTHER LINE.

SO INSTEAD OF LISTING IT THERE, IT SHOULD JUST BE ANOTHER LINE OF, OF THE HEIGHT AND, AND ALL THAT THE NAMES HAVE TO MATCH.

IT'S HARD TO READ.

WHAT IS THIS BOX? WHAT THIS, UH, PROPOSED AT T ANTENNA EQUIPMENT BEHIND IT PROPOSED AT T EQUIPMENT.

SO IS THERE A HEIGHT FOR THAT? UH, YES.

THAT, THAT SHOULD BE PROPOSED AT T AT T EQUIPMENT OR A PANEL ANTENNA? 64 FEET.

WHERE IS THAT ON THE SIDE?

[01:25:04]

THAT IS THIS RIGHT HERE THAT COMES TO THAT? IS THERE A REASON NOT OR COMMSCOPE THE VOICE UP.

IS THERE A REASON IT'S NOT CALLED COMMSCOPE ON THE SIDE OR IS IT I'M MISSING IT? UH, NO, WE JUST HAD IT AS PROPOSED, BUT OKAY, WE'LL WE'LL LABEL IT.

CAN YOU DO IT, MAKE THE MATCH SO THAT WE DON'T SPEND ALL THIS TIME TRYING TO SEE IF IT IS INDEED THE SAME ONE.

SO I I WOULD ACTUALLY JUST SAY REMOVE ALL OF THIS AND JUST PUT THIS TO ITS, UM, TO, TO THE, UH, TO THE LOCATION.

I'M GOING TO TELL YOU HOW TO DO THAT.

YEAH, I'M GOING TO TELL YOU THAT WE NEED TO KNOW WHICH ONES ARE THE FOR AND WHEN WE'RE TRYING TO MATCH UP ON IT'S, AND AS I SAID, THERE'S THAT EXTRA LINES ARE, UM, SO WHAT IT NOW READS AND PLEASE EVERYBODY TELL ME IF THIS IS NOT CLEAR, IT READS CORRECT SO THAT THERE IS NO CONFUSION REGARDING GOVERNMENT BUILDING TWO HEIGHTS OF EVERYTHING MUST BE INCLUDED.

THREE.

IS THE CHECK CHECK LINE ON A O2 A CABLE? IF SO, IT MUST BE UN UM, IT MUST BE ADDED IN THE WORK EXPLANATION.

IT MUST BE INCLUDED.

EXCUSE MY OWN HANDLER OR INCLUDE LIGHTING INFORMATION FOR ENTIRE AT AND T SITE FIVE INCLUDE SIGNAGE DOOR LOCATION ON DRAWINGS SIX.

THE DRAWING MUST INCLUDE EVERYTHING EACH G DRAW DOOR SHOULD BE, BUT THAT, THAT'S THE EXAMPLE WE KNOW, KNOW THAT IT IS THERE, BUT MUST INCLUDE EVERYTHING.

IT'S UH, SEVEN ID ALL DOORS, UM, HEIGHT BECAUSE THAT'S ON THE OTHER PLAN.

ONE OF THEM IS NOT HEIGHT OF PLATFORM OF WITH HANDRAIL 10, UH, AIR SCALE HEIGHT.

BY INCLUDING THIS, THIS DOES NOT MEAN THAT EVERYTHING ELSE IS IDENTIFIED.

IT JUST MEANS THAT THOSE ARE SPECIFIC ONES WE MENTIONED AT THAT TIME.

AND I, SO WHEN THE VERY FIRST THING, SECOND THING SAYS HEIGHTS OF EVERYTHING, UM, SHOW SIGNAGE, LOCATION ON INSIDE OF DOORS.

ANYTHING ELSE? FRANCIS DIANE, INSTEAD OF SAYING EVERYTHING, UM, SHOULD WE SAY, UM, WHERE IT GETS TRICKY, UM, EQUIPMENT DEPARTS.

AND HOW ABOUT ALL IDENTIFIED OBJECTS LISTED IN THE THING? BECAUSE THIS PARAGRAPH DOWN? SURE.

OKAY.

I DO JUST, UM, I I THINK THAT THAT WILL BE OKAY.

UM, I, I THINK THAT WE DO NEED TO CLEARLY DELINEATE THOUGH WHAT ADDITIONALLY NEEDS HEIGHTS BECAUSE I'M LOOKING AT THE T-MOBILE APPROVED CDS AND THEY DO NOT HAVE THE HEIGHT OF THAT, UH, ELEVATED PLATFORM WITH THE HANDRAIL.

UM, AND THAT APPLICATION WAS APPROVED.

SO I THINK THAT IT WOULD BE HELPFUL TO CLEARLY IDENTIFY EXACTLY WHAT HEIGHTS ARE MISSING ON THIS APPLICATION.

UM, SO THAT WE ENSURE THAT, YOU KNOW, UM, WE, WE'VE CAPTURED EVERYTHING ON THE NEXT GO AROUND.

WE HAVE DONE TO THE BEST OF OUR ABILITY.

WE HAVE NOW SPENT AN EXCESSIVE AMOUNT OF TIME TRYING TO ANSWER THAT QUESTION.

PLEASE REVIEW THE VIDEO AFTERWARDS.

I HAVE NOW WRITTEN ALL ITEMS IDENTIFIED IN THE QUESTION.

SO IT READS HEIGHTS OF ALL ITEMS IDENTIFIED IN THE QUESTION MUST BE INCLUDED.

FRANCIS, DIANE, ANYTHING ELSE THAT YOU CAN SEE? NO, I I THINK THEY GET THE POINT.

YEAH.

OKAY.

WHAT I, WHAT I DIDN'T SAY.

IT MAY BE INSURED THAT THEY WILL BE NO HIGHER THAN FIVE FEET.

UM, I IT IS SIGNAGE AND IT ALSO SAYS IN THE ANSWER, PLEASE SEE IMAGE BELOW.

THERE IS NO IMAGE BELOW.

OKAY.

SORRY ABOUT THAT.

[01:30:17]

AND IS THERE SOMEPLACE THAT IT'S HIGHLIGHTS THAT IT WILL NOT BE MORE THAN FIVE FEET ABOVE GROUND LEVEL? UH, AND YOU'RE REFERRING TO THAT SIGNS 3 0 9? UH, NO.

SO WE WILL ADD, WE WILL ADD THAT.

UM, AND DOES IT SAY SOMEPLACE WHAT THE SIGN WILL BE MADE OF? OH, OKAY.

THEY FORGOT TO ADD IT ON, BUT YEAH, IT IT'LL BE THE SAME THING.

ALUMINUM.

UM, DOES THAT SAY THAT SOMEPLACE? IT DOESN'T.

WE'LL WE'LL ADD THAT.

AND UH, REGARDING THE FIVE FEET THAT YOU HAD MENTIONED, IT SAYS NOT TO BE HIGHER THAN YOU CAN READ THE CODE IF SPECIFIES.

OKAY, SO WHAT I HAVE WRITTEN HERE IS CORRECT WITH REMOVAL OF THE WORD BELOW TWO ADDRESS HEIGHT, THREE MATERIAL, AND YOU WAS COMPLETE AND INSURANCE WAS COMPLETE.

AND SO WE'RE DONE.

SO WHAT WAS WE DEEMED COMPLETE? A, B, C, G, E AND F.

YOU NEED TO CON, UH, CORRECT MOUNT SCO.

G IN OTHER WORDS, GET A NEW NOTARY.

IS THAT NOTARY AVAILABLE? IS THAT THE COMMON NOTARY THAT YOU U NO, THAT'S THE, UH, THAT'S THE, THE THE PROPERTY OWNER, OH, I GUESS SAID NOTARY BECAUSE IT IS AN AFFIDAVIT.

I'M A NOTARY.

MM-HMM .

I KNOW SAID SOMETHING CHANGED AFTER, RIGHT? I NOTARIZED AND THEY TOOK AN NOTE THAT THE INFORMATION WAS ACCURATE, HAD THE SAME NOTARY, AND IN FACT THAT THAT NOTARY SEE WHAT THEY CAN DO.

DESCRIPTION OF THE WORK.

REMOVE FOR A SENTENCE WITH T OH ONE, UH, TWO.

MAKE THE LAST SENTENCE INTO TWO SENTENCES AND REMOVE THE WORD.

SO THREE.

REMOVE GROUND LEVEL FROM DRAWING A.

OH TWO REPLACED WITH GROUND, UH, WITH ROOFS.

LEVEL H IS COMPLETE.

I IS COMPLETE.

J IS COMPLETE.

K IS COMPLETE.

C DEPEND ON A 90.

THAT IS NINE ZERO ALUMINUM THAT SAY R SIGN DOES THAT THE ONLY ONE WE REALLY, WHERE IS IT? .

THAT'S ALUMINUM.

THAT'S ALUMINUM.

BUT IT'S NOT ANNOUNCED.

NO DEVICE WOULD SAVED ALL THE OTHER, YEAH, 'CAUSE WE HAD INITIALLY THOUGHT THAT, THAT, UM, THAT UNDER THOSE, UH, SIGNS YOU GUYS WANTED THAT WE DIDN'T REALIZE THAT IT WAS ONE SEPARATE SIGN THAT YOU WANTED.

SO WHEN WE ASKED, ASKED HIM TO ADD THAT THEY, I I GUESS WE, WE MISSED THAT.

YEAH, THERE WAS NO SIGN BEFORE.

NOW THERE'S A SIGN.

SO L IS COMPLETE, M IS COMPLETE, N IS NOT EXPLAINED.

SPRAY NEXT TO OR BEHIND THE ANTENNAS.

TWO CORRECT THE PERCENTAGE, UM, IT IS ROUNDED INCORRECTLY AND FOUR THREE OF THAT IT WILL STATE THAT IT WILL NOT EXCEED THE APPLICABLE FCC REGULATIONS.

THE REPORT O IS COMPLETE.

HE, UH, IS CORRECT, BUT WE WANTED, WE WANT THE LANGUAGE CORRECTED SO THAT IN THE FUTURE PEOPLE WON'T SAY YOU ACCEPTED THAT.

SO IT'S ON PAGE FIVE OF THE NOISE REPORT.

C 6.0 CONCLUSION.

REMOVE REST OF SENTENCE ORDINANCE.

AND THE FIRST SENTENCE, THIS IS BECAUSE THE REPORT.

OH, I'M READING FROM THE WRONG ONE.

SORRY.

NO I'M NOT.

THIS IS BECAUSE THE REPORT PROCEEDS.

OKAY.

UM,

[01:35:02]

THE IN IN SUBMISSION TO ADD GREENBURG TO SECTION SO THAT IT READS TOWN OF GREENBURG NOISE ORDINANCE CITED HEREIN TO COMPLETE R COMPLETE THAT'S INCOMPLETE ONE CORRECT.

SO THAT THE GOVERNMENT IS NOT CONFUSING.

CON THERE'S, SO THAT THERE IS NO CONFUSION REGARDING A GOVERNMENT BUILDING HEIGHT OF ALL ITEMS IDENTIFIED IN A QUESTION MUST BE INCLUDED IS THREE.

IS THE, IS THE CHECKED LINE ON A OH TWO A CABLE? IF SO, IT MUST BE INCLUDED IN THE WORK EXPLANATION FOUR INCLUDE LIGHTING INFORMATION FOR ENTIRE AT AND T SITE.

FIVE INCLUDE SIGNAGE DOOR LOCATIONS ON DRAWINGS.

UM, THE SIX, THE DRAWING MUST INCLUDE EVERYTHING.

EEG DOOR, WHICH WE KNOW IS ON THE OTHER DRAWING, BUT WE NEED THEM INCLUDED.

THEY REFERENCED ON THAT SEVEN ID ALL DOORS.

UM, UH, EIGHT SHOWS SIGNAGE, LOCATION ON INSIDE OF DOORS.

NINE.

HEIGHT OF PLATFORM, UH, WITH HANDRAIL.

10.

AIR SCALE HEIGHT T CORRECT.

REMOVAL OF, UH, COR CORRECT WITH REMOVAL OF WORD BELOW TWO.

ADDRESS HEIGHT THREE.

MATERIAL U WAS COMPLETE, B WAS ONE, TWO AND THREE WERE COMPLETE.

UM, I'D LIKE TO MAKE A MOTION TO BEFORE YOU DO THAT, GRACE, SINCE WE NOW KNOW THERE ARE TWO DOORS TO THE ROOF THERE GOING PHOTOS SIGNED ON ONE OF THE DOORS, THE PLAN SHOULD SHOW BOTH THOSE.

SO WHERE DO YOU WANT THAT ADDED? UNDER S UNDER AND A O AND SHOWN ON A O SEVEN 11.

IT'S, UM, PHOTO OF INSIDE OF BOTH.

YEAH.

MAY I MAKE THE MOTION THAT WE DEEM THIS APPLICATION INCOMPLETE? DO I HAVE A SECOND? SECOND.

ALL IN FAVOR? AYE.

AYE.

OKAY, MOTION CARRIES.

PARDON? MOTION CARRIES.

MOTION CARRIES.

NOW THAT YOU VOTED, YOU CAN MARK, I'M SORRY, NOW THAT YOU VOTED, YOU CAN MARK THAT BOX.

OH GEEZ.

THIS MUST BE MY GOD CLONING THEMSELVES INTO MY HOUSE.

PARDON? THEY'RE CLONING THEMSELVES IN MY THEY THEY THROW.

NOBODY WANTS TO.

[01:40:17]

WE'RE DONE HERE.

THIS IS FOR YOU TO LOOK AT.

THEN I WILL RUN IT UP STEVE.

SO, UH, WITH G UM, OKAY.

YEAH.

WHAT, WHAT'S STATED HERE? UH, REMOVE, REMOVE ANYTHING THAT'S THAT LABELS ROOF LEVEL OR REPLACE IT WITH ROOF LEVEL.

UH, GROUND LEVEL WITH ROOF LEVEL.

UH, OKAY, I THINK I'M GOOD WITH THAT.

THE NEAR LEVEL.

I'M GONNA HAVE TO TAKE THAT TO THE FF ENGINEER.

OKAY.

SO HERE, READ THAT.

UM, I NEED YOU TO INITIAL THROUGHOUT YEAH.

PAGE INITIAL WHERE I WROTE INITIAL INCOMPLETE AND YOU CAN INITIAL WHEREVER YOU WANT THROUGHOUT OR NOT.

SOME PEOPLE DO AND SOME PEOPLE DON'T.

AND DO YOU HAVE THAT, DID YOU GET THAT BACK TO ME? SO IT, I'M GOING TO RUN THIS UPSTAIRS.

MM-HMM .

AND FRANCIS.

SO WHEN YOU STOP RECORDING , SO I'M GONNA TAKE HERE IS YOUR COPY.

THANK YOU.

HERE'S YOUR COPY.

THE INITIAL, THE CHANGES.

I'M SORRY.

I DID, I OH, YOU DID.

SORRY FOR IT'S ALL.

OKAY.

OKAY, SO I MAKE THE MOTION THAT WE ADJOURN SECOND.

ALL IN FAVOR? UH, WHEN DO YOU THINK YOU'LL BE ABLE TO GET THE MATERIALS BACK TO US? UH, AS SOON AS POSSIBLE.

AS LONG AS, UH, 'CAUSE THESE, THESE DOCUMENTS TAKE A LONG TIME TO, TO PRINT, SO I WANT TO SAY HOPEFULLY IN THE NEXT TWO WEEKS.

OKAY.

WE WILL, YEAH, JUST LET US KNOW AND THEN WE'LL SCHEDULE ANOTHER MEETING.

ABSOLUTE.

YEP.

YOU HAD A MOTION.

AND SECOND SHE DID SECOND.

ALL THE MOTION TO ADJOURN.

SECOND.

ALL IN FAVOR ADJOURNED.

WE DID BILL.